on 11-27-2013 2:59 PM
HI Gurus ,
We are in the process of QM master data uplaoding in the system . I have created Inspection char in which assigned inspection method assigned to it . But at t
the time of upaloding "Inspection plan" system is not able to copy the "Inspection Method" from "Inspection Char " & it is asking again . We don't have
"Inspection Method " in "Inspection Plan " templates .
Please let me know how to update the Inspection plan from Inspection Char in the system .
Thanks ,
Regards ,
Aman
This is typical issue when you try to upload inspection plans through BDC. Try by LSMW using standard program method.
Else,
Mention the same inspection method, in inspection plan template again. You may need to modify the existing program for incorporating this additional field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.