Hi Experts,
We have a situation, where process orders are created in R/3, with certain basic start dates, but these basic start dates and hence the finished dates are getting changed by APO which should not happen.
For example, the below order was created on 21:11:2013 at 20:09:39, but it was changed to 22:11:2013 by APO by the CIF job when sent back to R/3.
Need help on why is this happening and how to rectify it.
Hi
As the order is forward scheduled and if any changes happened to this order in APO, has to be reflected in ECC and hence there is a possibility of the date getting changed. We need to see the date in the order while it was in APO and compare them to the one in ECC before the transfer.
Might be need to have more data to see why this is happening.
Thanks
Elan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prince,
We are facing the same issue in our system, can you please let us know if you found any fix for the issue.
Ram Mourya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Prince,
Are you doing gATP check while creating the Process order in ECC ? Is the scheduling config that does the rescheduling of orders enabled in your system which is possibly responsible for this behavior
Babu Kilari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.