on 11-21-2013 11:52 AM
Dear Experts,
Please help me, I have multiple WBS User Status. Management need the settings to restrict the user to create Material component after WBS Release. We have created user status REL - Released for WBS but after release user states not moved on REL.
Please let me know that which Business Transactions will be used in REL - Release user status and how it will move on REL.
Surjit Singh
In the WBS element click on the blue i next to the list of statuses, then click on the Business process tab. This will show you what is allowed or forbidden. Select a process and click on Trnasaction Analysis to see what status is controlling the process.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Something else is going on because I have created a User Status in a test system with just preventing the Material PR business process and I was stopped when I created a PR in ME51N.
How are your users creating PRs?
Make sure in the WBS that the User Status is active and hasn't been changed automatically per the settings in the Profile.
Dear Kel,
I am also facing this problem.
You are right as per your testing system not allows the creating of PR throguh ME51n and user sttus works fine.
But when you create PR through project systems in CJ20N by assigning material component to neiwork activity it not works.
I think sujit is also facing the same problem.
How to restice the PR creation with current user status setting through project system CJ20N
Regards,
Pradeep
Hi Pradeep and Sujit,
With material component assignment under NWA user status prohibits the PR creation though user are able to create PR by manually selecting field reservation relevance/purchase req. (RESBD-AUDISP) in component verview screen. To restrict this ,make use of "transaction and screen variants (SHD0)" to make this field non-editable. Also make sure that under control tab of network , field ' Res./Purc.req.' is non-editable.
Regards
Saurabh
Dear Sourabh,
You answer is to restice the PR creation permanently through project.
Here project PR are created from project screen through CJ20N.
Requirement is to restict the PR creation in slected user status's. After setting thses statuses still system allows to create PR from CJ20N but through Me51N it works fiine.
Please provide the solution for CJ20N
Regards,
Pradeep
Dear Sourabh,
User status already asigned to network type that why we came to know that user status settings are not working.
To craete the PR always we have to mantin the "Immidiatelly" in setting of field 'Res./Purch.req.' (CAUFVD-AUDISP) in control tab of network.
PLease replicate the sceneraio to know the system behaviour.
Regards,
Pradeep
Refer to SAP Note 497090.
User status cannot be used to prevent automatic PR creation from the Project.
There are 2 workarounds:
1. When you attach the component you need to set the PR/Res indicator to NEVER. The material will still show in the planned cost but no PR or reservation will be created. When you are ready to release it change the setting to IMMEDIATLEY.
2. Use a PR release procedure which will prevent the PR from becoming a PO unril it is released. This is a MM function.
Hi Pradeep,
In Network 'Change Status' ensure that you have maintained the relevant status profile there.
Also,please note that once the n/w is released then you have to maintain the new status profile in network manually (if system permits then only you can maintain) . If you cant then after release of the network the settings of OK02 and OPSC wont work .
Regards
Dear Saurabh
My organization need not to create material component from CJ20N after release of activity. So please let me know that how could we restrict the user.
I have created screen variant and set Res. / Pur. Req. "From Release" default but after release of activity when I create new material component system automatically set "Immediately" option in new.
Please suggest that what I do. It is very urgent.
Surjit Singh
Hi Saurabh
I alrady have done the changes in Network Profile but it's not work.
I need to restrict the user after release of activity. In attachment I have shown that the user are able to create the material componebt after release of activity and when he will create the component systen automatically assign Res./Pur. Req. indicator "3" which I have set "2" using screen varient.
Please check and suggest me.
Thanks and regards.
Hello Surjit,
It is standard Surjit. You have restricted the PR of material component until release of activity earlier.So,when you attached very first component "Res.Purc.Req." indicator is 'From release:2' . Then you released your activity and a PR was triggered for that component. Now,from now onwards if you attach any material further,system will create a PR immediately because the current status of your activity is REL(that is why it is coming as 3 automatically).User status and variant has served its purpose and now it's working as per standard.
Regards
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.