Hello Expert,
i have controlling area currency EUR but client is required to display report in project currency INR.
I have done the changes in RPC0 target currency is INR exchange rate current with ex rate type P as mentioned in planing profile as well.
but when we execute the cn41n/cns41 structure report is not displaying in INR currency still displaying EUR?
please help me out?
Regards,
Sanjeev
Hello Sanjeev
You can create a new form(report) using CJE5 (see KBA 1925431)
OR you can add the new functionality usign BAPI PS_FUNCTION_SWITCH
there is many notes on this
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Search the forum for CN41 and currency. there are many other discussions about this issue.
But, the CN41 reports only show values in Controlling Area currency.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.