CNS41 currency want to change INR instead of EUR

Former Member
0 Kudos

Hello Expert,

i have controlling area currency EUR but client is required to display report in project currency INR.

I have done the changes in RPC0 target currency is INR exchange rate current with ex rate type P as mentioned in planing profile as well.

but when we execute the cn41n/cns41 structure report is not displaying in INR currency still displaying EUR?

please help me out?

Regards,

Sanjeev

Accepted Solutions (0)

Answers (2)

Answers (2)

gerry_hodgins
Active Participant
0 Kudos

Hello Sanjeev

You can create a new form(report) using CJE5 (see KBA 1925431)

OR you can add the new functionality usign BAPI PS_FUNCTION_SWITCH

there is many notes on this

Former Member
0 Kudos

Search the forum for CN41 and currency.  there are many other discussions about this issue.