No costing variant exists in controlling scenario CPR1

Former Member
0 Kudos

Hi,

We are facing issues with Project Costing in cProjects. we are getting error "No costing variant exists in controlling scenario CPR1".

Costing variant is maintained in the Controlling CPR1 and other settings are looking fine. It would be great if someone can suggest the root cause for this issue.

Thanks in advance,

Prabu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I hope you have tied your controlling scenario with controlling area in next config step after defining controlling scenario. If you have done this already then please check whether costing variant is defined correctly (okkt).

Pramod

Former Member
0 Kudos

Hi Pramod,


The costing variant is there in OKKR transaction but not in OKKt. I have updated used the costing Variant PS06 ( PS06 exists in both OKKR and OKKT transaction) in the configuration but still i am getting the same error message.  Can you suggest me what else i am missing..

Thanks in advance,

Prabu

Former Member
0 Kudos

Hi Prabu,

Please check if this thread can help you.

https://scn.sap.com/thread/1803901

Also please check if you have mapped the project type with your Controlling scenario?

Regards,

Runjhun

Answers (0)