Hi,
We are facing issues with Project Costing in cProjects. we are getting error "No costing variant exists in controlling scenario CPR1".
Costing variant is maintained in the Controlling CPR1 and other settings are looking fine. It would be great if someone can suggest the root cause for this issue.
Thanks in advance,
Prabu
Hi,
I hope you have tied your controlling scenario with controlling area in next config step after defining controlling scenario. If you have done this already then please check whether costing variant is defined correctly (okkt).
Pramod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pramod,
The costing variant is there in OKKR transaction but not in OKKt. I have updated used the costing Variant PS06 ( PS06 exists in both OKKR and OKKT transaction) in the configuration but still i am getting the same error message. Can you suggest me what else i am missing..
Thanks in advance,
Prabu
Hi Prabu,
Please check if this thread can help you.
https://scn.sap.com/thread/1803901
Also please check if you have mapped the project type with your Controlling scenario?
Regards,
Runjhun
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.