on 11-11-2013 6:10 PM
Hi,
My requirement is if first operation was not recorded, system wouldn't allow me to record against second operation
Let me know Is there any SPRO setting to create a dependency for operations in an inspection plan or we have to go for exit.
thnx
srini
you can make RR mandetory for operation by OPK4 setting ,but operation wise control or dependency is not possible by std way.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No. Nothing standard for this in QM.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.