on 11-08-2013 8:38 PM
Hi Expert,
I actually have the next process:
When a message is fail on SMQ2, all the next message are in queue, and I delete the fail or save LUW for process the other message. With the save LUW the fail message is move at SMQ3, and Check in this trx the error and solution.
My question is:
Move this fail message, can be automatic from SMQ2 to SMQ3?
How is this configuration?
Plis help me.
Regards Friends.
Check this SAP Note 441269 and also refer the below blog which can provide other alternatives on handling the Queue issues.
~Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I believe you need to do some customization to the standard reports to achieve this.
We have separate reports to move failed messages to smq3 & activating queue's for processing remaining messages.
can you check the below thread on the same topic?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |