on 11-06-2013 7:07 PM
Hi dear Forum,
I want to sync SLD content from a Netweaver 7.0 to Solution MAnager 7.1 SLD. Both CIM Model and CR content are on the same level. I configured Bridge in 2 SLD's
How can I trigger sync on my Netweaver 7.0 System?
Thanks in advance
Hello Jose Luis,
Please check the following link:
https://help.sap.com/saphelp_sm71_sp05/helpdata/en/a5/971735dd184f5c8d943c6cf423d13a/content.htm
You have to add the SLD data source in the LMDB configuration using transaction SOLMAN_SETUP and the route System Preparation Prepare Landscape Description Set Up LMDB. Over there you can add a SLD and start with the full synchronization.
Also I think there is an error in the document since it says SLD based on SAP Netweaver 7.0 is not compatible with LMDB but as far as I remember our SLD is based on Netweaver 7.0 and it's working correctly.
Best regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No problem. I'm sorry for misunderstanding your question as I thought you wanted to sync an external SLD with the Solution Manager LMDB.
I'm afraid that sync an external NW 7.0 SLD with Solution Manager 7.1 SLD using a bridge connection won't work properly, we tried some time ago but the SLD didn't sync the data correctly.
Best regards.