Include production orders in ATP check - prod orders spanning multiple days?

former_member607794
Participant
0 Kudos

Hi all,

We include production orders as available inventory in our ATP check.  Currently, production orders are scheduled to start and complete within the same day, and we use a GR processing time of 1 day so that ATP; sees the product as available the day after production.

However, for other reasons on the production side, the business is now considering creating production orders for large quantities, spanning multiple days. So for example, the start date/time on the order is Nov 10 at 08:00 and the finish date/time is Nov 13 at 13:00.  With our current approach, the entire quantity of that order would be available on Nov 14 (because of the 1 day GR time) in our ATP calculation. 

Is there any way to base the availability of the production order on the start date instead of the finish date?  Or somehow 'spread' the ATP quantities over several days?

Thanks much in advance!

Allison

Accepted Solutions (0)

Answers (1)

Answers (1)

rahul_vishwakarma2
Contributor
0 Kudos

Hi Friend,

     Kindly use the Forwarding Scheduling (Automatic forwarding) and make the segment "SETUP".

     or

     Try this link : http://help.sap.com/saphelp_erp60_sp/helpdata/en/b1/c042b7439a11d189410000e829fbbd/content.htm

Hope this will help you.

Regards,

Kundan