on 11-04-2013 9:31 AM
Hello,
when starting the Role Usage Synchronization in ERM for a production system the job does not run correctly.
Job history is not showing any error, but:
31 | 11/4/13 3:05:45 AM | Ready | Job created |
31 | 11/4/13 3:06:23 AM | Running | Job running |
31 | 11/4/13 3:06:23 AM | Completed | Job completed |
The connector for the production system was created just before creating the job.
Is a re-start of ERM required before the sync job can be released? Is there any other setting missing?
For other, already available systems, the job ran correctly without issues.
We are on GRC 5.3 SP19.
Thanks,
Tanja
Got the solution, forgot to run the initial load jobs in ERM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.