Hello,

when starting the Role Usage Synchronization in ERM for a production system the job does not run correctly.

Job history is not showing any error, but:

3111/4/13 3:05:45 AMReadyJob created
3111/4/13 3:06:23 AMRunningJob running
3111/4/13 3:06:23 AMCompletedJob completed

The connector for the production system was created just before creating the job.

Is a re-start of ERM required before the sync job can be released? Is there any other setting missing?

For other, already available systems, the job ran correctly without issues.

We are on GRC 5.3 SP19.

Thanks,

Tanja

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Got the solution, forgot to run the initial load jobs in ERM

  • ORG Value Synch
  • Transaction Synch Job
  • Activity Synch Job