Hi there, We have a few Abap programs that have started running quite a bit longer than normal in POSDM. How do I go about checking to see "how far" the program has run? .e.g we have 500 stores, which store is currently being processed?
11-01-2013 6:10 AM
Hi Wayne,
If your ABAP programs are scheduled in background, you can see their progress in transaction SM37. In SM37 transaction, you can select your job name and click on Log button which will show the steps completed so far.