on 10-30-2013 3:26 PM
HI Gurus,
I have deleted multiple times the SNP ditribution demand planned in planning book but they are reappring in APO.They are not in ECC (PO's)
Thanks for your help in advance
Vijay KH
Hi Vijay,
Run CCR for combination of Product and Destination Location for PO and PReq elements.
Once APO and ECC are in sync then you can delete the PReqs at destination location either through RRP3, SNP Planning book, RRP4 or RLCDELTE transactions.
Distribution demand Planned should be seen in SNP Planning book at source location on account of Purchase requisitions (Not POs) available at destination location.
Regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vijay, Normally the key figure "distribution demand planned" is not editable in SNP planning book. To delete it, you should go to the target location, and delete the corresponding order in "distribution demand receipt" key figure, and press save button. Or you can use report /sapapo/rlcdelete to delete the order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.