I tried to Send Planned orders to R/3 in CCR?..

Former Member
0 Kudos

I tried to Send Planned orders to R/3 in CCR?.. Even after trying it many times.. its not transferring.. Please suggest me to rectify it

Accepted Solutions (0)

Answers (1)

Answers (1)

ravi_malpani
Active Participant
0 Kudos

Hi Santosh,

If the orders are not being transferred to ECC then check the transaction /sapapo/cq in APO. You should see a queue in ECC inbound. This queue will give you the details of the error. Most probably it would be some incorrect master data in ECC. Eg. Check Production version validity to date or if the version has been checked.

Are you using PPM or PDS?

If you are using PPM and are facing problem with SNP planned orders then it is quite possible that the Production version in SNP PPM is not updated with that available in ECC. In this case you should delete and regenrate the SNP PPM.

Hope this helps.

Regards,

Ravi

Former Member
0 Kudos

Hi Ravi,

Thanks for the reply.

Regards,