Hi,
I have release 20000 budget in WBS. There is actual budget of Rs. 15000 after Material or finance postings. Then I settle the WBS values to AUC through CJ88 (Automatic settlement), the actual amount becomes double i.e. Rs. 30000 and the available budget shown is negative of 10000 in reports (like S_ALR_87013558). However system allows to post for another Rs. 10000, with out releasing the budget ,what is the reason to double the actual budget.
Please suggest
Regards
Rao
Hi bhavani,
Check in report CJI3 your line items for actual costs ( here you have your actual costs and your settlemet costs)
You have to exclude your settlement agaist AuC and then check the rest of the costs.
If here you display :30000 then you have to analyse your costs
If here you display 15.000 then report S_ALR.... Is not correct, check the values in table RPSCO,
If they are not correct -- execute tx CJEN to regenerate the values in RPSCO
If they are correct check If you have changed the standadr report and modify the values
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The problem not with the report, system consume the budget double ,because of this I need to give double budget ,As per my observations...Process is
1) System create the AUC at the time of WBS release
2) After actual postings system consume the budget.
3) At the time of automatic settlement system consume the budget again.
as per my observations CWIP G/L also created as a statically cost element.
budget consume.
Regards
Rao