How to filter planned orders from ECC to APO?

Former Member
0 Kudos

Hi SAP Experts.

We have an issue in the project and need your help.

For some SKU we will plan part of the requirements in APO and part in another system (legacy).

For that reason we need to filter those planned orders created by the external system to do not impact the MRP run.

How can we filter those some planned orders for the same SKU?

We try to create a different depot and during the planned order create by the external system, we use the differente depot, and filter that depot in CIF enhancement. But the bussiness team does not agree in create a new depot.

Does anyone has any other idea?

Thanks in advance.

Thiago

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

HI Thiago,

First for which horizon you want to plan in APO and for which horizon in ECC (Longterm or short term)?

If you wish to plan short tern in APO then maintain the resource calender for that period as -30 & +30 so that system will plan for this period only rest of the period you can plan in legasy period.

If you wish to plan long term in APO then maintain the SNP horizon as 3 to 4 weeks so that APO will plan for long term and you can plan short term in legacy system.

Thanks

Sravan

Former Member
0 Kudos

Hi Sravan,

thanks for your attention.

We need the same horizon for both APO and ECC.

We addressed this requirement, copying the production version to a second one, and the orders created by the legacy system, only use the second production version, and we filter the planned orders by the production version during CIF integration.

Regards