Hi Friends,
I have one query is MRP area becomes mandatory to maintain in material master in ECC if this material has XO MRP Type.
Many Regards,
Umang Sharma
Thank You friends for your help, it solved now.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Umang,
No, it is not mandatory to set MRP areas for MRP type X0 in ECC material master. Generally we use MRP type X0 when we have APO system integrated with ECC system.
Rgds
Sourabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is no need to MRP area as already answered sourabh.
how you reach creating MRP area? any error said create MRP area?
your are expecting STO from where to where? one plant to other? if yes, is material maintained in both plant, transportation lane created?
system, will not suggest to create MRP area on its own.. its business decision.
Pravin
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.