Hi All,
we have factory calendar attached to ship to party. Saturday/sunday is not working day in factory calendar.
we are creating a sales order for the ship to party. The requested delivery date =30.11.2013 but the system gives a confirmed delivery date on
7.12.13.
But 7th Dec'13 is a saturday
Why is system giving a non working day as confirmed schedule line date ?
What is missing.
Also for information we have GATP in our system
regards
Pamela
Dear,
Request delivery date is on Saturday 30.11.2013 but system confirmed on 7.12.2013.
My query is if that SAT and SUN days are non working days then why you want requested delivery date is 30.11.2013 as on SAT?
If your FAC is not having SAT and SUN then when a movement you maintained 30.11.2013 then system shall show you goods confirm on working day.
Another query is ,you need to think of that why system has taken a long time to the confirm goods.
Have you assigned delivery block in sales order ?.If yes ,pls check,what settings ( check ,Field-Def .Period ) you kept in OVZ7
Thanks,
Naren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1.Check once again the correct Factory calendar is assigned to Ship to party or not.
2. Check once again the Factory calendar working days.
It should be checked only from Monday to Friday as per your requirement.
3. Check you Sales org,Plant and Shipping point. since in all these places Factory calendar is assigned, may at some places it is different.
Thanks,
Srinu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.