Hi Experts,

I need your suggestion about Quantity confirmation behaviour in the case of Sales BOM.

Scenario:

Sales BOM:

1 PC Mat C = 1 PC Mat A + 2 PC Mat B

Mat C is just a Text Material. Pricing will be at Mat C level.

Quantity deduction will happen at Mat A and Mat B (Component) Level.

Available Qty:

Mat A = 280 Qty

Mat B = 430 Qty

Sales Order Line Item for Customer:

10) Mat C = 300 Qty

11) Mat A = 300 Qty

12) Mat B = 600 Qty

Confirmed Line Item will be as below at Schedule Line:

10) Mat C = 300 Qty

11) mat A = 280 Qty

12) Mat B = 430 Qty

Now, requirement is, System should always confirm Component Qty as per Sales BOM Ratio and it's minimum availability.

So in Above case, it should have been

10) Mat C = 215 Qty

11) Mat A = 215 Qty

12) Mat B = 430 Qty

Now how can I achieve this type of Scenario, please suggest. If any customization of Exit needs to be used then what logic should I use and at which place.

Regards,

MJ.

Accepted Solutions (0)

Answers (1)

Answers (1)

neeraj_lal
Contributor
0 Kudos

MJ,

looks like I am not able to get your requirement completely....... To me it looks like part shipment (Partial Delivery scenario) where BOM components materals stocks are avaiable to get only 215  qty of material C?

Where system is require to create part delivery... Multiple schedule line? Do you mean to partial delivery allowed option is not working in this case?

Regards

mahendra_jani3
Contributor
0 Kudos

Hi Neeraj,

First thanks for your response.

Actually, In my Case, System is confirming as per normal behavior where If Component quantitiy is less, then system is confirming accordingly.

If I have to send material in Pair only in the case of Sales BOM so if 1 PC Mat C is ordered by customer, then I will have to send (1 PC Mat A + 2 PC Mat B) , If my Qty is confirmed (1 PC Mat A + 1 PC Mat B) I can not deliver that goods.

How can I always, achieve that system should only confirm quantity as per CS02 for Main Material. Means, If 5 Mat C is ordered then, System Must confirm ( 5 PC Mat A + 10 PC Mat B). If system has only 8 PC Mat B then confirmation should happen (4 PC Mat A + 8 PC Mat B).

Hope my requirement is clear now.

Regards,

MJ.

mahendra_jani3
Contributor
0 Kudos

Hi Neeraj,

Finally my issue resolved. My Issue was even though there used to be Delivery Grouping for BOM system was copying quantity same line normal line items as I have explained in above response.

I did below Item Category determination in Delivery:

LF + ERLA + Blank + Blank + TAQ

LF + NORM + Blank + TAQ + TAE

After this updates, system started to adhere the Delivery Grouping and determining quantities properly.

Regards,

MJ.

neeraj_lal
Contributor
0 Kudos

Hi MJ,

Thanks for sharing solution.