on 10-21-2013 5:16 AM
Dear Experts,
We have SNP heuristic set up in our system to generate the SNP planned orders. Sometimes for unknown reason, in CCR report, it will show that some planned orders are in ECC but not in APO, and the only way to reconcile it is selecting 'send APO'. After that, i will see the planned order become PPDS planned orders in APO. Since SNP planned orders and PPDS planned order has different category in our SNP planning book (SNP planned order goes to 'Production (planned)' key figure and PPDS planned order goes to 'Production (Confirmed)' key figure), and users will complain why planned orders appear in 'Production (Confirmed)' key figure instead of 'Production (planned)' key figure.
I have read several threads about this, it looks like it is a standard CIF behaviour of this result. But is there a way to make planned orders shown as SNP planned order outside SNP horizon after CCR?
Thank you very much!
Best Regards,
Anna
Unfortunately no... its a pain.
SAP now allows SNP Pur Req's to be created but they have't add the functionality for SNP Planned Orders yet.
Ken
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
These orders moved from APO and Delete from APO Only.
So Order Exists in ECC Itself
Then you Ran the CCR Job......u found the Order Exists in ECC then you moved in APO.
So when the Order moves from ECC will be created as PPDS Order....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anna,
Is the error code in the CCR report 152 ?
If yes. You can CIF the planned orders to APO as SNP Order by using checking the below option in CFM2.
"Create SNP Planned Order at Transfer of Planned Orders".
Please note you need to do a initial transfer of planned orders of affected products by doing a exclude and include from the Planned Order Integration Model. Ensure that the above given option is ticked while activating you integration model.
Cheers
Ajay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You are right that it is standard SAP behavior. And yes, it is same in SCM 7.0 also.
Btw, did you try to find out why those orders are stuck in CIF and hence we find those at CCR? May be resolving the root cause so that these orders don't need manual reconciliation would be a good way to avoid those!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you guys, do you happen to know if SCM7 will have solution to this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In our system, we too face a similar issue. My understanding is that since we select the option "Send to APO" in CCR, system considers it as a manual action (change) and hence the order category changes to PPDS.
We follow a way of working by which after sending the order to APO, we delete the orders using RRP4 transaction and then re-run heuristics to regenerate SNP Orders.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.