Can Project be changed after CR is authorized?

former_member210667
Participant
0 Kudos

Hi,

Please let us know if Project can be changed after CR is authorized?

I tried :

deleting transport and withdraw the Change document but still not able to change project

Let me know how to change project?

Regards,

Neni

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Neni,

You can change the project assignment in More Option, as per Solman 7.1

I am not sure in 7.0 this option is available or not.

As per my understanding you should be able to chnage the project if you have not released Transport Requests & Tasks.

May be this option available for particular CD status may be during 'In development' status.

You need to check if you have authorization to do so.  Let me know once you try this.

Regards

PK

former_member210667
Participant
0 Kudos

when I try to do Edit it says -

Details No changes possible in document                         (There are not transport associated with this Change document)

Former Member
0 Kudos

Hi Neni,

You can try to use Charm Flexible, if you have NC with TR's that not yet released.

Go into normal change and press More-Reassign Normal Change choose other project.

Normal change will change project and related CR also

BUT! it is only works if 1 CR = 1 NC

Regards DAN

former_member210667
Participant
0 Kudos

Tr is deleted from the change document

Where I can find the

"Go into normal change and press More-Reassign Normal Change choose other project."