Availability check required at sales order level with wbs element

neeraj_ahuja3
Participant
0 Kudos

Hi Experts

please help me out by this situation where we made one sales order for 100 Item and every line item is trading Goods and having 02 availability check into

material master, now when a new purchase has come into any item  out of 100 item and i am going to check availability check is not happening , even

Material GRN is happened into project(special stock) + wbs Combination.

Rgds

Pankaj Agarwal

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Were the stocks updated with special stock indicator "Q" which is intended for PROJECT STOCK ??.  Also share your settings of OVZ9 for 02/AQ

G. Lakshmipathi

neeraj_ahuja3
Participant
0 Kudos

Hi Lakshimiptahi

your are going quite right , actually its project Q stock only and Availability Window of 02/AQ is only tick  includes sales Requirement/include Deliveries.

Rgds

Pankaj Agarwal

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Pankaj

At the schedule line level, please check whether schedule line category is activated for availability check . If  Yes, then pl check at the item level, in the account assignment tab, have you maintained the correct WBS element for which stock is maintained?

Rgds

Pronojit Gupta