Hi QM Gurus,

My business want  one inspection plan for  all materials, so for this I created one inspection plan and I assigned to multiple materials in same plant but while creating inspection lot plan is assigned only one material not for al what is the problem can any body have idea kindly guide me what was the cause.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

You have assigned multiple materials with single Inspection Plan. When you create lot, you are not getting that Inspection Plan assigned to all materials, its getting assigned for only one material.

Check the validity date for that assignment. Check whether any other Inspection plans assigned to other materials.

former_member42743
Active Contributor
0 Kudos

I'm not clear on what you mean.  You said you created a plan and assigned all materials to it.  Then you said you created a plan and only one material was assigned.

Can you clarify?

CS

lakshmi_prasad7
Contributor
0 Kudos

Crig,

sorry for confuse my requirement is

I assigned multiple materials with single Inspection Plan. When inspection lot trigger inspection plan  not assigning  into assignment materials.

former_member42743
Active Contributor