Hi friends,

I am trying to find out whether it is possible to distribute hours of an employee against an activity automatically without getting into CMP2 transaction where manual distribution is to be done. I want to avoid manual distribution and want system to distribute hours automaticall after the resource is allocated to network activity in Personnel Assignment tab in CJ20N transaction.

If this possible what are the prerequisites for the same.

Regards,

Gireesh

Accepted Solutions (0)

Answers (1)

Answers (1)

sunil_yadav2
Active Contributor
0 Kudos

Hi Gireesh,

I do not think this functionality is there in the SAP standard because of multiple reasons.

if you have more than 1 resource performing that activity so you will not get flexibility.

SAP does not have this functionality because getting flexibility to distribute the work according to user.

thanks