Stock transfer intracompany between plant with WBS stock non val.

Former Member
0 Kudos

Hi Gurus,

I have a big problem.

in my system I have the following scenario:

one Project (WBS) for realization of protoype for customer. The project stock is  non valuated.

I created a sales order with account assignment WBS Element.

The prototype must be produced and assembled in PLANT A, but a component of BOM is realized in PLANT B of the same WBS Element.

I produce a component with Product Order and I do a good receipt from order to WBE stock /plant B.  the component  is stored in stock non valuated.

I create a Stock transport order  for muving material from PLANT B to Plant A.

account assigment category = Q, from Plant B to Plant A

account assigment the same WBS Element.

And  I try to do outbound delivery for  stock transp. order .

Unfortunatelly I display

the error message "Message no. CN769, WBSelement V.67.13.008.01 has different inventory valuation"

I have check but the stock is rightly non valuated.

But I havechecked in the EKPO TABLE:  the stock tranport order have a valuated value = M (valuated stock) .

Why this happened?

Can you help me?

Thank you for your cooperation

Federica Usai

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

As a first thought, try using Account Assignment "P" on the STO.

former_member195427
Active Contributor
0 Kudos

Hi,

Try to transfer this stock to general stock first then to non valuated project stock.

May be MvtType 411Q can be of help.

Former Member
0 Kudos

Hi Saurabh,

tks for you reply,

the SAP documentation declares that this movement  (stock non valuated beetween PLANT)is possible. You can see the link http://help.sap.com/saphelp_45b/helpdata/en/4d/2b92c943ad11d189410000e829fbbd/content.htm.the workarond that you suggest me not good, because the material would require of standard price valuation.

Thank you for cooperation

Federica