ROEMPROACT2 - Planned orders issue

Former Member
0 Kudos

hi all,

We are sending in planned orders per supplier to sap snc SNI monitor using ROEMPROACT2 program. I have done the spro setting to reset the times series every time we get message "Reset Time Series for Incoming ProductActivityNotifications".

But the old data is not getting deleted. Can you please let us know time series used to store the planned receipts in SNI monitor and also is there any way i can delete the data?

Please let me know if i have missed out on any other configuration/ data.

thanks,

mahesh.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member194108
Participant
0 Kudos

Hi Mahesh,

You can use /SCA/DM_DELETEINV  to delete the Old data and then you can run ROEMPROACT2 pragram to share inventory.

Regards,

Rahul Sharma

Former Member
0 Kudos

thanks. Just did that deleted the data and resent the data supplierwise but the planned orders are not getting displayed per vendor.

Please let us know if we are missing any setting to show the planned receipts per vendor in SNI monitor

Former Member
0 Kudos

Hi

In EHP6 with ECC6.0 for ROEMPROACT2 how can I trigger XML to SAP SNC without using IDoc? Please help.

Thanks,Kiran

Former Member
0 Kudos

Hi Kiran,

Check out below link:

http://scn.sap.com/thread/2080646

Regards,