Dear Expert,
I have question on recording of Sub process Design Assessment.
When we perform control design assessment and test of effectiveness the evaluation are recording with the control in the evaluation tab of the
control.
In the similar manner there should be an evaluation tab on the sub process level which can record the assessment performed for sub-process
but there is no evaluation tab present.
Am I missing any configuration on this.
Thanks in advance,
Regards,
Sahil.
Hi Sahil
There is no tab "evaluation" in subprocess as far my knowledge is concerned, but there is a specific report "subprocess design assessment" in Reports work center in Assessment work center, where we can have an overview.
Regards
Prateek Lal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prateek,
Thank for the information. Even I knew about the same, but though of asking the experts about the evaluation tab for subprocess assessment.
Regards,
Sahil.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.