cancel
Showing results for 
Search instead for 
Did you mean: 

Sub-process Design Assessment Evaluation

Former Member
0 Kudos

Dear Expert,

I have question on recording of Sub process Design Assessment.

When we perform control design assessment and test of effectiveness the evaluation are recording with the control in the evaluation tab of the

control.

In the similar manner there should be an evaluation tab on the sub process level which can record the assessment performed for sub-process

but there is no evaluation tab present.

Am I missing any configuration on this.

Thanks in advance,

Regards,

Sahil.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sahil

There is no tab "evaluation" in subprocess as far my knowledge is concerned, but there is a specific report "subprocess design assessment" in Reports work center in Assessment work center, where we can have an overview.

Regards

Prateek Lal

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Prateek,

Thank for the information. Even I knew about the same, but though of asking the experts about the evaluation tab for subprocess assessment.

Regards,

Sahil.