Hi Gurus,
During optimization runs, will it be advisable to run CIF integration models of masters in parallel
Kindly advice
No, it is quite not advisable. You may even get some error with that. Stop CIF before optimizer run (especially in night jobs) would be a good and suggested option. Please refer to note 1228423 for more detailed information.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramana,
I would agree with Ada on this, stopping CIF queues during any planning engine run (Optimizer / CTM / Heuristics) is best practice to avoid system inconsistencies.
Rgds
Sourabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.