SAP PS Network requirement still showing after delivery

Former Member
0 Kudos

We have a case where the Network requirement is still showing as a demand in MD04 when the delivery has been done?

How is/are these Network demands reduced?

David

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Did you try those correction programs yet. is so let us know what is resolution.

Did you see the material "withdrawal qty" field checked in table RESB? or not.

Thanks,

Sudhakar

Rachel_Tang
Advisor
Advisor
0 Kudos

try report RM06C020 which is in SAP note 115899

or check SAP note 633119

former_member195427
Active Contributor
0 Kudos

Hi,

I am not sure.. but can you please check the reserved material in project builder under 'Proc. Param' tab of material and 'Tick' the 'Final Issue' check box for that material.

If possible,please check in testing server first then in production.

Regards