Please find the issue, when I see  the Key figure value “ Operational Target Invt Qty” the value is  different  between Total and detail all  ,macro is in default only, Can you Please suggest

This issue is there in all the systems production and test

Example: Selection:

Product:

5070-3114

5070-3115

Location: 3220186281

Please find the attachment for the issue

and also can you please exalin the  Forward Calculation macro how it works

FORWARD_CALC()

FORWARD_CALC( number of days ; area containing the values ; area containing the number of working days in a period) returns the sum of the values in the area over the number of days specified. If the number of days does not coincide with the end of the period, the value for this last period is calculated proportionally.

Period 1 2 3 4 5 6

Demand 100 120 130 120 100

Working 20 22 21 22 20
days

In the above example for period 1, FORWARD_CALC ( 63; ..) returns the value 350 (100 + 120 + 130). FORWARD_CALC ( 74;...) returns 410 (100 + 120 + 130 + 120 11*22).

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Kiran,

Set the macro to 'Level change' also and check.

Let us know the SCM version used in this case as some of the older versions had problems with Agg / Dissagg.

Regards,

Vishwanath