CTS+ on PI 7.31 with RC=12

Former Member
0 Kudos

Hello Experts,

I have setup CTS+ on our PI 7.31 SP07 (Dual Stack) system following the steps shared by Mr. Yogesh Patel (http://scn.sap.com/docs/DOC-30177).  Our DEV system (P1D) is the transport domain.  P1Q is our QA system (clustered).  PRD is yet to be installed.  The only deviations I made are with the service user IDs I used (due to naming convention we use) and I did not include SLD yet (DEPLOY_SLD_URL).  Everything looked fine until we tried to do a test transport wherein it fails and gives RC=12.

I tried to search for SAP notes from SMP and the internet thinking that someone has already encountered this error and was able to identify the cause of the error and fixed it.  Unfortunately, the only similar issues I found were on SolMan and EP. 

Any information which may help fix this issue would be much appreciated.

Thanks in advance.

Rey

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rey,

Please fallow this Link:http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/e088cec0-700d-2f10-5a86-d11bed0b9...

Notes for CTS issues:

Some issues related to AS ABAP during CTS imports are explained in SAP Note

1139406 – CTS+ Import Issues.

Assertion Error that occurs during CTS+ export is explained in SAP Note 1351604 –

CTS+ export Assertion Error.

Fallow below SND Blog:

https://scn.sap.com/people/michal.krawczyk2/blog.

Thanks

Sreenath

Former Member
0 Kudos

Hello Sreenath,

These are very useful links.  It gave me a clearer understanding how CTS+ works and how it should be setup.  Thank you very much.