on 10-07-2013 8:27 PM
Hi,
I have requirement to configure the scenario Single sales order Multiple deliveries.
I have gone through the SAP SCN Blogs and help. I found following scenarios:
Single Sales order with multiple schedule lines to single ShipTo party.
Multiple Sales orders to Single Delivery (Single ShipTo Location)
Customer is going to send us Single PO - Single sales order will be crated in SAP with different ShipTO parties at item level.
This scenario will be : Single Sales order with multiple ShipTo's(Multiple Delivery locations)
For this I have to configure GATP and GTS.
Can you suggest me best possible solution? Other than middleware split or ABAP development.
Thanks
Sree
Hi Sreenath,
As mentioned this can be achieved by giving different ship-to-parties and shipping point at the item level of the sales order for the line items, where-in, there will be different deliveries created for one sales order.
Hope this helps!!
Regards,
Sambit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.