cancel
Showing results for 
Search instead for 
Did you mean: 

Automatic scheduling in SAP-PPM (Project Management)

Former Member
0 Kudos

We need to keep the automatic scheduling on even after Project Release (PPM Project Management). Which meas, this should happen at Project Save and the user need not click on the Schedule button explicitly...

Possible? How?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

I think this thread from Mariano will be helpful.

http://scn.sap.com/thread/3411123

Regards,

Runjhun

Former Member
0 Kudos

You probably already know this, but this is not possible in standard. If this is really needed you will have to do a custom (I think relatively simple) enhancement. I've had this requirement in the past, but managed to convince the business that it is not the best practice for most scenarios.