PP/DS planning time fence differs

former_member476084
Participant
0 Kudos

Hi gurus

A product has 14 days of time fence in apo but when i try to view that product in product view its showing 21 days.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member458819
Active Participant
0 Kudos

attach the Screenshots so we can check

Sunil

Former Member
0 Kudos

Hi Debasis,

If not already, please check production calendar  for the location.

Planning Time Fence maintained in APO product master  is  in Workdays.

The system determines the workdays from the production calendar for the location.

Hope this gives some insight.

Regards

Datta


former_member476084
Participant
0 Kudos

Hi Datta

I have checked the location master and found out that calendar is not defined for that plant.

Regards

Debasis

Former Member
0 Kudos

Hello Debasis,

Could you please check the GR time for that product location?

May be due to GR time its coming 21 days.

Regards,

Vivek