Former Member
0 Kudos

Hi,

If in schedule line, I switch off the availability check and switch on the TOR. what does it mean  functionally. Can some one explain by example as to what impact we can see !

1) will the backward and forward scheduling happen if ATP check is switch off ?

2) What other impact will have functionaly on switching off the avalability check

3) How will the schedule lines get confirmed since ATP check will not happen (opening stock+receipts -issues ) ?

regards

Pamela

Accepted Solutions (1)

Accepted Solutions (1)

mahendra_jani3
Contributor
0 Kudos

Hi Pamela,

If in schedule line, I switch off the availability check and switch on the TOR. what does it mean  functionally.

  • If Availability check is off then Stock confirmation based on ATP will not happen. All the order quantity will be shown as confirmed quantity in sales Order.

Example : Mat A Order quantity is 1000 PC and available quantity is 10 PC. But if at schedule line level if Availability check is off then system will confirm all 1000 PC.

  • If TOR is switch on then Requirement will be transferred to MRP, so still Production Planning can be happened based on the same and you will be able to see Requirement in MD04.

1) will the backward and forward scheduling happen if ATP check is switch off ?

  • No Backward or Forward scheduling will happen. For at that point of time, system will consider all the stock is always available.

2) What other impact will have functionaly on switching off the avalability check

  • No other impact other than quantity confirmation based on ATP will not work.

3) How will the schedule lines get confirmed since ATP check will not happen (opening stock+receipts -issues ) ?

  • Schedule line gets confirmed for all the quantity because, when Availability check is off system assumes that company has unlimited resource and will be able to produce all the goods asked on that specific date.
  • considering the same, it confirms all the stock on that particular date itself. No checking of (opening stock+receipts -issues ).

Regards,

MJ.

Answers (4)

Answers (4)

former_member182378
Active Contributor
0 Kudos

Pamela,

3) How will the schedule lines get confirmed since ATP check will not happen (opening stock+receipts -issues ) ?

The value populating in "Confirmed qty" at the schedule line level, in a sales order - is a result / outcome.

The system can check availability or not check availability, and then populate the value in field "Confirmed qty".

If the setting is to deactivate availability check, then the qty to be delivery (order qty) is automatically set as the confirmed qty, even if there is no stock in that plant and storage location.

Examples -

1. For serivce items, the availability check is deactivated (not considered).

Repair of TVs, even if there is zero qty in the plant and storage location, the confirmed qty shall be equal to the order qty.

2. In a business where lots of stock is stored and there is never a situation of non-availability of stock.

Always there shall be 2 months of stock (Laptops) in the plant, then no need to do an availability check.

obrarajesh
Explorer
0 Kudos

Hi Pamela,

Hope this diagram will help

Thanks,

Rajesh Kumar

former_member182378
Active Contributor
0 Kudos

Rajesh,

How does your diagram help the OP?

former_member184065
Active Contributor
0 Kudos

Dear,

If in schedule line, I switch off the availability check and switch on the TOR. what does it mean  functionally. Can some one explain by example as to what impact we can see !

Even if uncheck AV in VOV6 AV will be carried out because system will give you preference for AV in requirement class level instead of VOV6 level.If AV is carrying out then you will find out at sales order level in which date you issued and how much you had like all details and one more thing is you can this AV details in MD04 and CO09 but if AV is not carrying then you can not see these details in that transactions.

In Requirement Class ,If you switch of the TOR with switched on availability then you will get one error.Please check in your system also.

Let me know ,your understanding on below query.

What is AV and TOR ? what is exactly difference ?

1) will the backward and forward scheduling happen if ATP check is switch off ?

Up to me ,No ,it wont happen .

2) What other impact will have functionally on switching off the availability check

You cant see day to day activities of material in sales order level as well as in MD04 and CO09. AV is very nice tool in SAP to see material details especially in sales order level.

3) How will the schedule lines get confirmed since ATP check will not happen (opening stock+receipts -issues ) ?

Not getting ,provide small example on this if possible.

If you stock then it will be confirmed at sales order level when AV is off if not ,no confirmation .

Kindly ,let me know if you want any further help on this.

Thanks,

Naren

former_member182378
Active Contributor
0 Kudos

Narendra,

Even if uncheck AV in VOV6 AV will be carried out because system will give you preference for AV in requirement class level instead of VOV6 level.

The above is incorrect!

If in the schedule line category, field AVC is deactivated, then in that sales order the availability check shall not happen.

Same logic for TOR also.

If in requirement class AVC and TOR are deactivated, then the settings of the same in the schedule line category do not matter. Both AVC and TOR shall not happen (at sales order level).

jignesh_mehta3
Active Contributor
0 Kudos

Hello Pamela,

Would it not be a good idea to try the above case in your Development server yourself? 

Thanks,

Jignesh Mehta

Former Member
0 Kudos

Hi Jigensh,

we have many developments related to availability check. So not sure of the results. So asked this question !

regards

Pamela