Responsible cost center could not be changed in WBS after settlement

Former Member
0 Kudos

Hello,

We faced with problem: responsible cost center could not be changed after investment WBS settlement.

Error message occured:

KI247 "Cost center  belongs to business area & instead of &"

I found related SAP note "0000160499 KI247 with release investment measure", but it have implemented already in our system.

Please advice how to solve this issue.

Best regards,

Kristina

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

System does not let you change the CTR if actual costs exists and settlement performed. Talk to your CO guy to remove the costs CTR and redo the settlement etc whatever require. Then change CTR.

Try this note 415157 - AS02: Business area stored in spite of termination -

Thanks,

Sudhakar

Former Member
0 Kudos

Hi,

thank you for the reply and suggestions. SAP note was implemented in the system.

First of all we will reverse WBS element settlement and then change the responsible cost center in  the WBS master data.

Best regars,

Kristina

Answers (1)

Answers (1)

Former Member
0 Kudos

Look at SAP Note 889326 for another correction.  And SAP Note 552051 for more information when a change can be made to the org elements on a capital WBS.

Also pay particular attention if the indicator for "Business area financial statements" is

activated in any of the company codes on the WBS or to which the Resp Cost Center or Responsible Cost Center are assigned.  Also check for consistency on the Company Codes and Business Areas asigned to all of the Cost Centers.   

Once you have made postings to a business area it cannot be changed.

Former Member
0 Kudos

Hi,

thank you for the replies. All SAP notes were downloaded in the system. But your advices were really useful.

Best regards,

Kristina