on 09-25-2013 8:28 PM
Hi All,
Planned order created by SNP run (Heuristic) always has start and end date same.
The same planned order when hit the ECC, it get rescheduled and has different start and end date.
Example:
Planned Order Start Date End Date
In APO 31/10/2013 31/10/2013
In ECC 29/10/2013 31/10/2013
In PDS, activity duration (fixed) is 1 day and I believe it could be the reason.
ECC, calculates the correct duration (Actual Order Quantity*Standard Activity Hours in Recipe / Base Quantity) and schedules the order.
How the activity duration (fixed) figure populates in PDS?
Please provide the info what could be the reason for SNP planned order have always similar start and end date.
Let me know if required any information to undersatnd the facts.
Regards,
Deepak
Hi Deepak,
SNP explosion will only respect the bucket consumption (variable or fixed). Please check whether you have the bucket consumption set in your PDS. Bucket consumption will not be filled automatically during PPDS -> SNP PDS conversion. You have to take care of it in a BADI. (Sample code in note 853241).
Best Regards,
Ada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deeapk,
You have already checked the non relevance of the notes.
Just wanted to point out that some notes do require specifc SP even in version 7.0 of SCM.
For example for OSS note 1462965 correction is delivered in Service Pack 7 of version 7.0.
Please ignore if you have already checked this aspect.
regards
Datta
Hi Deepak,
If you are generating SNP PDS through SAP ECC CIF transfer, then there are chances of the variable bucket capacity consumption of a SNP PDS being calculated wrongly depending up on the version of your SCM environment.
Please check following OSS notes for applicability.
Hope these note give some insight to you.
Regards
Datta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Deepak,
This is a standard behavior while creating a SNP PDS.
Suppose you have only one operation in the Recipe with a machine duration of 21 hours for a base quantity of 100. Lets assume that the resource on which this operation is carried out is available for 24 hours.
When this PV is CIFFed to APO to create a SNP PDS, it does a rough calculation on the the basis of base quantity. In this example it will be calculated as 1 day (it is always Fixed). Even if the planned order is created for 120 units/150 units the duration will be 1 day fixed.
You may test this behavior by reducing the availability time of resource and could see that the duration changes to 2/3 days Fixed.
Thanks | Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.