Hello Gurus,

                       I want to generate planned order without PDS . So what i am thinking is send the toplevel product with inhouse production (without any PDS) . So when i run CTM/Heuristics will it generate planned orders still .

If yes What is the need of PDS .

Regards,

Abhinav

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Nick,

You are right. Heuristics creates Planned orders without a Source of Supply when a SNP PDS does not exist. A PDS will have BOM information, Recipe & Resource.

So this Planned order will not generate Dependent demand on the Component, No resource loading.

Trust this helps in answering your question.

Thanks,

Chandra

Former Member
0 Kudos

HI Chandra,You are absolutly right.

former_member906762
Participant
0 Kudos

Hello Chandra ,

                          How about CTM .

Regards,

Nick

Former Member
0 Kudos

Sorry, I have not worked on CTM. So couldn't comment much.

Thanks | Chandra

former_member492024
Active Participant
0 Kudos

Hello Nick,

Not sure if I understood correctly your doubt.

Well, it seems CTM or heuristic will create the planned orders without PDS for the header product. The need of the PDS would be to plan the components if existent, and to create a source for them.

Regards,

Michel Bohn