Hi All,

We have the option of setting the projects with 'Calendar' or 'Standard' working days.

When set as the 'Standard working days', does it exclude public holidays? Say when setting the schedule with planned offsets?

Also, is there a way to specify region specific public holidays for Sourcing to exclude?

Thanks & Regards,

Subhasini

Accepted Solutions (1)

Accepted Solutions (1)

former_member200421
Active Participant
0 Kudos

Hi Subhasini,

Using Standard working days does not provide any functionality to exclude holidays.  It's basic functionality that just considers a 5 day work week and excludes weekends as opposed to a Calendar week which considers all 7 days.

Hope this is useful,

Rosemary 

Former Member
0 Kudos

Thanks Rosemary.

Regards,

Subhasini