Convert multiple reservations into individual PR through MRP run

Former Member
0 Kudos

Hi Everyone,

We are facing issue in MRP.

We have PM order for stock material which creates reservation for the material. If there are multiple PM orders on the same date then we have multiple reservation for that particular material. After MRP Run; system creates a single PR clubbing all the reservation quantities into it and there is no account assignment in the PR.

As per the client requirement; there should be separate PR for each reservation which contains the order details (account assignment details) as per the schedule. We have already set Individual requirment (01) in MRP4 view, Lot size as EX and Availability check as 02 in the material master.

It is working fine if we use Item category 'N' for the same material in PM order component tab.

Kindly suggest what else is needed to configure, to get separate PR for each reservation through MRP run.

Regards,

GNK

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi GNK,

Individual/collective  requirement only work in case of make to order scenario which is not applicable in case of plant maintenance.

In standard SAP if the requirements of one day are also combined to one procurement proposal for the lot-for-lot order quantities (lot size EX) (see documentation for lot-for-lot order quantity). Separate procurement proposals can only be achieved if you work withmake-to-order production. Here, the requirements are managed in separate planning segments of the stock/requirements list.

Hope clear to you. Also refer the OSS Notes: 140802 & 550568 for more details about it.

You can use the BADI MD_CHANGE_MRP_DATA to have separate PR for requirement on same day.


Regards,

R.Brahmankar