I have created a "Quality notification" with QM order for calculating the "Non conformity" costs for both In house and vendor quality defects. I have assigned the cost center in the Notification type and the same is appearing in Notification.
My issue is how and where to enter the non conformity costs incurred for doing the rework activity in the notification
J.Balakrishnan
Hi
Pleas go through it. It will definitely help you.
http://help.sap.com/saphelp_46c/helpdata/es/e4/e312d81ff611d4b2cd0050da4ceab0/content.htm
regards
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Create QM order & assign the same to notification
Use KB21N & enter the desire activity type.
Check the same with KOB1 or KSB1
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
All costs accumulated in a QM order must be confirmed and settled in the Controlling (CO) component of the SAP System.
You can input activity quantity into QM order through KB21N (Record activity).
Choose 'Order' for screen variant, input some value and confirm.
I suggest you set this up with your CO team.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.