cancel
Showing results for 
Search instead for 
Did you mean: 

Material Availability Date not Updated but Allocated Stock is available

0 Kudos

Hi, folks!

We are encountering an issue wherein the material availability date of an item in the sales order does not get update even when the allocated stock for that item is already available.

Scenario:

Item 100 has a MAD of 24.09.2013. This date is coming from the AB confirmation delivery date in the PO which is 23.09.2013 + 1 GR day. However, the allocated stock for that item is already available as of 13.09.2013. Even if we trigger the ATP check in the sales order, nothing happens. Only when removing the AB confirmation from the PO does the MAD gets updated correctly. However, we need to have the MAD reflect the correct date which is 13.09.2013 since the stocks are already available.

Looking forward to your inputs!

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Found out the answer - OSS note 149421 to fix the issue

Answers (0)