New Procure tu Pay scenario vs. Standard Scenario

Former Member
0 Kudos

Hi Experts , I'm working with SRM 7.02 with ECC 6.06. Our model is SRM Classic scenario and MM-SUS + ROS.

Our scenario is SC-> SOCO-> BID / AUCTION -> PO or  Contract in ERP -> SUS , ... etc

We don't want to use CPPR because every requisitions will be created directly in SRM by the requester users, but we wanted to avoid purchasers to access both SRM and ERP. Then we thought that by implementing this P2P scenario and using /SAPSRM/OP(ST)_PURCHASER_ERPSRM_EHP1 roles we will improve this situation, but my question is :

It is usefull to implement P2P if we don't want to use CPPR ??

What's your recommendation?

Thank you!!

Celeste

Accepted Solutions (1)

Accepted Solutions (1)

preeti_negi
Explorer
0 Kudos

Answers (1)

Answers (1)

former_member208675
Active Contributor
0 Kudos

Hi,

CPPR transfers PR from ECC to SRM.

It's not must to implement CPPR.

There would not be any issue in your P2P scenario without CPPR.