on 09-11-2013 3:54 PM
Hi Experts,
I am facing a bit peculiar problem as below.
When I supplier creates confirmation(whole requested qty) for a PO and clicks on 'check' button
due qty = zero
due qty(conf.) = requested qty
Then without changing anything if they publishes the same then
due qty = requested qty
due conf qty = requested qty (in confirmation schedule line)
due conf qty = zero (in request schedule line)
conf status at both item and header level is 'confirmed'
If reopen the PO in SNC then
due qty = requested qty
due conf qty = zero (in both request and confirmation line) but still the conf status at both item and header level is 'not confirmed'
Please suggest me where am I doing wrong.
It seems due qty calculation is going wrong.
Thanks & Regards
Praaty
Hi Experts,
There was issue with assigning the change profile to BPs. When I removed and again created the assignment it started working properly.
Thanks for your expert advices.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pratyusha,
If customer changes (change in delivery date, qty etc) a PO item which has been already confirmed, then status will become "Open".
1. Due Quantity in request will become equal to Request Quantity.
2. Confirmation line should be removed. And, supplier will have to re-confirm the PO item.
Is that not happening?
Regards
Shekhar
Is that not happening?
Regards
Shekhar
Is that no
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.