how to trasnfer material from one wbs to other of same project

former_member604117
Participant
0 Kudos

Hi

The client wants from wbs A assigned to project x having 10 qty of matrial ,4 matrial need to be  reassigned to wbs b assigned to project x.

so wbs a will have 6 matrial and wbs b will  have four material. how this will be done

John

Message was edited by: Mohamed Rafi - Next time when you need any info or solution, search the forum first.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

You can transfer stock from One WBS to Other WBS by using T Code MB1B, Use Movement Type 415 Q (Transfer Posting Project to Project).

Have one suggestion, please search forum before posting and you will get lots of responses in the past.

Thanks,

Sudhakar

former_member209919
Active Contributor
0 Kudos

Hi John,

Could you try in MB1B with mvt 415Q?