Dear Expert,
I've encountered an unusual error here.
I've created separate project for normal change (ZERPN01) and urgent change (ZERPU02) both have identical logical system.
For Normal change, everything is smooth until transport to PRD. For Urgent change, after I approve the Request for Change, Urgent Change document generated but this error "There is no active tasklist in the assigned project" occur. Tasklist are active and /tmwflow/charmchk shows all green
I've search for answers and some of them said that it was caused my authorization issue but I've tried to put SAP_ALL but still can't.
I've raised OSS message for this but still no response for 4 days.
Is there any other possible solution for this ?
Please advise,
Best regards,
Carroll
Hello Carroll, have you check that post from Prakhar Saxena ?
http://scn.sap.com/docs/DOC-31352
http://scn.sap.com/docs/DOC-44166
Regards,
Luis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
The problem is solved.
Re-check RFC connections and please note that RFC connections for Solution Manager should be 'Trusted' connection.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.