Can any one explain about heuristic planning engine ,,,how it works and functionality in SNP with details.
Do not send help.sap.com links, please explain in general manner with detail explanation.
Thanks for you support
GRPN
Hi
Please go through the Below Link Which Gives you More Information on SNP Heuristics
http://scmgmt.blogspot.in/2009/02/heuristic-based-planning_19.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello GRPN,
I think it is quite hard to explain everything in details, since it is quite complicated with the whole logic. But basically it works like:
- Apply data into planning book, and execute macro calculation
- Read data based on key figure function, to get the target stock level and stock on hand for each period
- Calculate horizons and source of supplies
- Cover demand shortage for each bucket, considering procurement type and the validity of source of supply. This process only set a quantity to procure for each bucket.
- The above is calculated for all location/products selecated, and for the found components if the setting is checked
- Creation of the planned orders and planned stock transfers in liveCache. In case of planned orders, it involves PPM/PDS explosion and scheduling; in case of planned stock transfers, complicated scheduling happens.
Best Regards,
Ada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.