on 03-09-2007 11:20 AM
Hello everyone,
We are going to use the following BAdI's to create PDS
/SAPAPO/CURTO_CREATE
and for CTM
CREATE_CTM_PDS
Questions:-
If we create the PDS for CTM does this still create them for PP/DS? so would the table entries be double? (one for the PP/DS PDS and one for the CTM PDS).
And cane we make the naming of the CTM PDS different to the PP/DS PDS (so insert CTM in front of all the CTM PDS).
Thanks in advance.
Guy
Guy:
When you generate integration model for PDS you choose Rough cut planning and PDS type SNP for CTM, where as PDS for PP/DS goes by its own type with Detailed planning option and when you CIF it over to APO you can see the PDS to check the difference between CTM PDS or PP/DS PDS by there type.
I hope this help.
Mono
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.