Dear Experts,
I need to provide functional overview of QM General Task in one my documents in which I need to clearly explain why we are uploading General Task Lists/ Equipment Task list , Dependencies and the prerequisites for the upload. Kindly help me in his regard.
Kindly go through the following link
http://help.sap.com/saphelp_erp2004/helpdata/en/2d/352298448c11d189420000e829fbbd/content.htm
These type of task lists are used in Calibration
Basic difference between Equipment/Genral task list is as the name suggest, equipment task list is specific of a particular equipment whereas general task list can be used for any equipment.
Equipment tasklist -IA01
Pre requisite: Equipment master, inspection point, MIC, Inspection method, sampling procedure etc
General tasklist : IA05
Pre requisite: inspection point, MIC, Inspection method, sampling procedure etc
System will take reference of maintenance plan for equipment in case of general task list.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you have same requirement??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You mean to say Inspection plan (QM task list), if it is then it contains master inspection chara., Inspection method, sampling proc., sampling Drawing procedure i.e. Quality related data.
If you want to check the QC of material then you have to create Inspection plan & assign required MIC, methods in it.
You can mass upload by creating BDC program.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.