Hello Experts,
I would like to know,Can we influence the ship date in SNC PO line item instead of calculating from TL transportation duration.
The requirement is to update the ship date from ECC header to SNC PO ship date in line item level.
Appreciate your help!!
Sridhar,
SAP has provided the /SCA/SCHEDULE Business Add-In (BAdI) to modify the scheduling logic.
More details are available in this link : http://help.sap.com/saphelp_SCM700_ehp02/helpdata/en/2b/adabf6bdd540f09d10f30351ff45df/content.htm?f...
Regards,
Bharath