report /RPM/FICO_INT_PLANNING - conversion factor not maintd

0 Kudos

I get an error message by using the Report /RPM/FICO_INT_PLANNING to get financial data from an ERP- System to the SAP PPM- System.

I think the Problem is caused due to the Portfolio part use the unit ZPD (person day) and in Fi/CO the time is recorded in hours.

I have already checked the units in Portfolio, which are based on seconds. ZPD = 28.000 s and Hour = 3.600 s

Have somebody an idea where I have to put in a conversion factor?

The message is: Conversion factor not maintd for unit H Portf. and Proj. Mgmt unit ******

Thanks in advance

Bernhard

Accepted Solutions (1)

Accepted Solutions (1)

former_member209919
Active Contributor
0 Kudos

Hi Bernhard,

Check in the FI/CO system if you have configured the conversion :

SPRO --> Integration with other mySAP.com components --> PPM -->Portfolio Management -->  Convert Working time units.

Regards

0 Kudos

Hi Clara,

thank you very much for your answer..

I have also added the conversion factor in the FI/CO System for H --> PD and now I can execute the the report without an error.

Best Regards