on 09-05-2013 12:46 PM
I get an error message by using the Report /RPM/FICO_INT_PLANNING to get financial data from an ERP- System to the SAP PPM- System.
I think the Problem is caused due to the Portfolio part use the unit ZPD (person day) and in Fi/CO the time is recorded in hours.
I have already checked the units in Portfolio, which are based on seconds. ZPD = 28.000 s and Hour = 3.600 s
Have somebody an idea where I have to put in a conversion factor?
The message is: Conversion factor not maintd for unit H Portf. and Proj. Mgmt unit ******
Thanks in advance
Bernhard
Hi Bernhard,
Check in the FI/CO system if you have configured the conversion :
SPRO --> Integration with other mySAP.com components --> PPM -->Portfolio Management --> Convert Working time units.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
7 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.